A can do a work in 9 days while B can do the same work in 18 days, A and B started the work and worked for 4 days then B left the work. In what time A will complete the work? A. 4 Days B. 2 Days C. 3 Days (Your Answer) D. 3.5 Days I M NOT ABLE TO UNDERSTAND HOW THE ANS CAME 3..PLZ EXPLAIN
I think for question no 4 the ans is 9 days how it will be 7 can you please explain me
ReplyDeleteI think for question no 4 the ans is 9 days how it will be 7 can you please explain me
ReplyDeleteA can do a work in 9 days while B can do the same work in 18 days, A and B started the work and worked for 4 days then B left the work. In what time A will complete the work?
ReplyDeleteA. 4 Days
B. 2 Days
C. 3 Days (Your Answer)
D. 3.5 Days
I M NOT ABLE TO UNDERSTAND HOW THE ANS CAME 3..PLZ EXPLAIN
Hello Samriti,
DeleteThanks for notifying, this has been corrected the right answer is 6.